Introduction to Rainwater Monitoring and Construction of Small Reservoirs and Dam Safety Monitoring

Layout Schematic Diagram:

Red: Dam axis
Blue: Monitoring cross-sections, generally no less than 3. The spacing is 20–50 m within 300 m, and 50–100 m beyond 300 m. Yellow: Monitoring longitudinal sections, generally no less than 4. One shall be arranged above the normal pool level on the upstream dam slope.

断面示意图:


Hydrological and rainfall monitoring: real-time water level and rainfall data to provide timely and accurate data support for water storage regulation, flood control and drought relief.
Rainfall: real-time rainfall and cumulative rainfall. Rainfall directly affects the water level.
Water level: flood limit water level, normal storage water level, design flood level, etc.
Image and video monitoring: real-time monitoring of water color, floating debris, abnormal conditions and so on for more timely and efficient management.
Voice intercom and broadcast: for alarm purposes, etc.



Site Construction:
1. Inspect the site with reservoir data, design plans and drawings: mark and record installation positions (latitude and longitude, etc.), the number of staff gauges required, pole height, cross-arm length, required cable length, check the elevation of benchmark points, confirm and record on-site power supply, network signal and traffic conditions, etc.
2. Verify survey data, formulate construction plans, purchase equipment and auxiliary materials, customize poles, organize personnel, etc.
3. Excavate and pour foundations, dig cable trenches, etc.
4. Assemble and fix equipment and poles, lay and backfill cables, etc.
5. Commission equipment and conduct joint debugging with the platform.



GNSS Monitoring: Using BeiDou high-precision positioning technology, it observes the tiny overall deformation of the dam, builds a statistical analysis model, and predicts the long-term variation trend of the deformed body. The observation accuracy can reach the millimeter level.
Manual Observation: Regularly observe the deformation state of the dam body with equipment such as precision levels, and collect and sort out the observation data.


Site Construction:
1. Conduct site survey by combining reservoir data, design plans and drawings: mark and record installation positions (latitude and longitude, etc.), required cable lengths, monitoring points, check benchmark elevations, confirm and record on-site power supply, on-site network signals, on-site traffic conditions, etc.
2. Verify survey data, formulate construction plans, purchase equipment and auxiliary materials, customize poles (observation piers), arrange personnel, etc.
3. Excavate and pour foundations, dig cable trenches, etc.
4. Assemble and fix equipment and poles, lay and backfill cables, etc.
5. Debug equipment and complete joint commissioning with the platform.

GNSS Station:

Manual observation:


Seepage Pressure Monitoring: Seepage not only causes the reservoir to lose stored water, but also can easily trigger seepage deformation such as piping and soil flow.
The water surface line of seepage inside the dam body is called the phreatic line. Real-time knowledge of the elevation of the phreatic line, combined with the safe phreatic line elevation, improves the timeliness, promptness and scientific nature of dam safety monitoring.
Saturation line schematic:

A key factor in the stability of an earth-rock dam is the position of the phreatic line (the fully saturated zone of soil within the earth-rock dam). In a safe dam, this saturated zone is well confined below the ground surface.


Site Construction:
1. Conduct site survey by referring to reservoir data, design schemes and drawings: mark and record installation positions (latitude and longitude, etc.), drilling depth of piezometer holes, required lengths of piezometer tubes and cables, confirm and record on-site power supply, network signal, traffic conditions and other information.
2. Verify survey data, formulate construction plans, procure equipment and auxiliary materials, arrange poles, customize piezometer tubes, organize personnel, etc.
3. Drill piezometer holes, excavate and pour foundations, dig cable trenches, etc.
4. Install piezometer tubes and osmotic pressure gauges, assemble and fix poles, fill out installation verification forms, lay and backfill cables, fabricate orifice protection devices, etc.
5. Carry out equipment commissioning and joint debugging with the platform.




Seepage Monitoring: Seepage water is collected into catch drains for visual monitoring to understand the seepage conditions of hydraulic structures and their foundations. It helps analyze and judge whether the conditions are normal, as well as the extent and causes of potential adverse impacts, providing a basis for maintenance, repair and safe operation of the project.


Site Construction:
1. Inspect the site with reservoir data, design plans and drawings: mark and record installation locations (latitude and longitude, etc.), lengths of seepage collection ditches and cables, verify and record on-site power supply, network signal, site traffic conditions, etc.
2. Confirm survey data, develop construction plans, procure equipment and auxiliary materials, customize poles, arrange personnel, etc.
3. Construct seepage collection ditches, excavate and pour foundations, dig cable trenches, etc.
4. Assemble and fix weir gauges and poles, lay and backfill cables, fabricate protective devices, etc.
5. Conduct equipment commissioning and joint platform debugging.


Water level staff:
Vertical staff gauges shall be installed in accordance with the relevant requirements specified in the Standard for Stage Observation (GB/T50138-2010). Manual observations shall be carried out regularly for verification against automatic observations.

1. The staff gauge consists of a 1 m tall, approximately 10 cm wide plate made of enamel or stainless steel, with a resolution of 1 cm. (Other dimensions can be customized.)
In use, the gauge plate is fixed onto gauge posts. A set of gauge posts is arranged along the water level measurement section and fitted with gauge plates to form a vertical staff gauge.
2. Gauge posts are made of concrete and firmly anchored on the bank slope or upstream dam face. The water level scales of adjacent gauge posts shall overlap appropriately (e.g., 20 cm) to ensure readings can be taken at any water level.
3. After installation, the zero elevation of each staff gauge shall be determined by precise leveling. The water level elevation is obtained by adding the zero elevation of the gauge to the scale reading taken from the gauge plate.
4. Where the structure at the measurement section has a suitable vertical face, gauge plates may be mounted directly on the vertical face of the structure.

Radar Water Level Gauge:
1. The on-site installation of the radar water level gauge is very simple. Just mount the water level gauge on a prefabricated pole bracket or the dam body. As shown in the figure

(1) Avoid locations with abundant floating debris on the water surface during installation.
(2) No other objects should be present within a certain range below the water level gauge to prevent reflection that leads to measurement errors.
(3) When installing the instrument, ensure the maximum liquid level does not enter the measurement blind zone.
(4) Ground the instrument and implement lightning protection measures.
(5) Route the signal cable inside a protective conduit for protection.

Bubble water level gauge:
When the upstream slope is gentle and the radar water level gauge installed on the dam body cannot measure the dead water level, a bubbler pressure water level gauge may be adopted. The installation schematic is shown in the figure.


The bubbler water level gauge blows air through an air tube to a fixed measuring point underwater to balance the gas pressure inside the air tube with the hydrostatic pressure at the measuring point. Water level measurement is achieved by measuring the pressure within the air tube, and its sensor is installed above the water surface.
① The layout of the air tube is the most critical step in the installation of a bubbler pressure water level gauge. The following principles shall be followed for air tube layout:
a) The air tube shall run down smoothly and be laid along a straight line as much as possible.
b) The length of the air tube should not exceed 150 m; curved sections of the air tube shall not have sharp bends, and the air tube shall be arranged along a smooth path.
c) The end of the air tube shall be secured inside the protective tube to prevent the air tube from swaying in the water and affecting measurement accuracy.
d) Heavy and stable high-density concrete blocks shall be anchored at key positions on the riverbank to fix the air tube and avoid risks from floods or bank collapse. Alternatively, the air tube may be fastened to existing stable structures.
② Fixed installation of the air chamber
Secure the air reservoir in place (fastened to sturdy metal with screws or by welding) before installing the protective tube, then proceed with installation. Only the metal section above the water needs to be fixed during installation.

Rain gauge:
The rainfall observation site shall be selected in an open and flat area free from the influence of abrupt terrain, trees, buildings and smoke. There shall be no tall crops, trees or similar objects within 20 meters around the rainfall monitoring facilities. Obstacles shall be kept away from the rain gauge. If obstacles cannot be avoided, the ratio of the distance from the obstacle to the rain gauge to the height of the obstacle shall not be less than two, so as to ensure that the rainfall observed at this site can represent the precipitation depth on the horizontal ground.

① Check the integrity and sensitivity of the instrument before installation.
② Mount and secure the rain gauge, level it, and ensure stable installation.
③ Level the tipping bucket bracket: inspect and adjust the tipping bucket to a horizontal position.
④ Install the output signal cable: connect it to the telemetry terminal, fasten the outer cylinder and tighten the screws.
⑤ After installation, recheck whether the installation is correct and whether the instrument operates normally,
and verify that the measurement accuracy meets the requirements.
Cameras:
1. Video monitoring points should preferably be arranged at the dam, spillway, discharge culvert and other locations, focusing on monitoring the overall dam condition, while covering the staff gauge, inlet (outlet) of the spillway, outlet of the discharge culvert, seepage behind the dam, etc.
2. Video monitoring points on the dam crest may be deployed together with rainfall and water level stations, with integrated station construction and centralized power supply; other video monitoring points can be set up independently.
3. Cameras shall be installed in locations with an unobstructed view and sufficient light, at a height of no less than 2 meters above the ground, and shall be equipped with waterproof, dustproof and anti-theft protections.

Gnss:
(1) Excavate a foundation pit of 60×60×80 cm at the selected point (the specific dimensions shall comply with site conditions and the design scheme);
(2) Fabricate the pouring formwork for the observation pier, and make a square formwork of 60×60×20 cm (the specific dimensions shall comply with site conditions and the design scheme);
(3) Use cement with a strength grade of no less than 325, and mix concrete in accordance with the strength standard of C25 concrete;
(4) Place the reinforcement cage and the fabricated formwork, pour concrete, and vibrate until the concrete is level with the formwork;
(5) Remove the formwork after standing for 12 hours.
(6) Install the equipment, fix the vertical pole, mount the equipment on the forced centering device, and connect the cables.
(7) Commission the equipment: assign IP addresses for each monitoring point, configure the IP address and port number on the main unit, perform commissioning, and record and save the results.

Observation Pier Requirements
1) Excavate to a relatively fixed position and cast the reinforced concrete base and shaft.
2) Benchmarks shall be arranged on the hillsides of both banks. The layout positions shall be firm and reliable to avoid natural and human disturbances. The benchmarks adopt an integral reinforced concrete structure, with the column height greater than 1.2 m. For working benchmarks embedded on rock foundations, the base may be cast directly on the rock. For working benchmarks embedded on soil foundations or additional non-fixed working benchmarks, the base must be embedded at least 0.6 m below the ground or dam surface into undisturbed soil.
3) The base measures 1 m × 1 m × 0.4 m. The shaft is a frustum connected to the base; the top dimension of the shaft is 0.3 m × 0.3 m and the bottom dimension is 0.6 m × 0.6 m. The height of working benchmarks is 1.5 m, and the height of observation piers and check benchmarks is 0.9 m (specific dimensions shall comply with the design scheme).
4) A forced centering base plate shall be embedded at the top, and the mean square error of the base plate shall be less than 0.2 mm.
5) A concrete structure shall be cast on the pier base, which shall be in close contact with the pier base, and leveling marks shall be embedded simultaneously.
6) If the collimation line method is adopted, the centers of the forced centering base plates of all measuring points shall lie on the collimation line, with the deviation not greater than 10 mm and the inclination not greater than 4″.
Base point observation pier:

Observation pier for horizontal displacement measuring point:

Vertical displacement measuring point observation pier:

Vertical displacement observation pier:

Benchmark:
Basic benchmark points shall be surveyed and transferred from national third-order or higher benchmark points with leveling measurement not lower than the third-order standard.
Benchmark points are generally made of concrete and buried deep below the frost line. A corrosion-resistant hemispherical metal marker is embedded at the top of the benchmark stone.


Piezometer:
Construction sequence:
(1) Hole drilling
(2) Piezometer fabrication
(3) Piezometer installation
(4) Hole sealing
(5) Sensitivity test
(6) Orifice protection
(7) Form recording


(1) Borehole Drilling
Drilling shall be carried out with a Model 150 geological drill. The opening diameter is 100–110 mm. Dry drilling is adopted. Drilling with mud for wall stabilization or clean water circulation is strictly prohibited. Casing can be used for wall stabilization to prevent hole collapse. Core logging and description shall be performed. Upon completion of drilling, hole inclination shall be measured to accurately determine the measuring point position.
(2) Manufacture of Piezometer Tube
A piezometer tube consists of a permeable section and a riser section. The permeable section can be fabricated from riser pipe material with an area opening ratio of approximately 10%–20%. The shape of holes is not restricted, but they shall be evenly arranged with burr-free inner walls. The permeable section is about 2 m long. Its exterior is wrapped with non-woven geotextile sufficient to prevent soil particles from entering, and the pipe bottom is sealed. The length of the riser is determined based on pipe material and installation convenience. External threads are preferred for joints at both ends, connected by outer coupling fittings.
(3) Installation of Piezometer Tube
Before installation, a comprehensive inspection shall be conducted and records made for the borehole depth, hole bottom elevation, water level inside the hole, hole collapse condition, as well as the fabrication quality of the piezometer tube, length of each pipe segment, joints and pipe caps.
Before lowering the pipe, approximately 10 cm of filter material shall be placed at the hole bottom. During pipe lowering, all connections shall be tightly assembled, the hoisting shall be secure, and the pipe shall be kept straight. After positioning, the pipe bottom elevation and water level inside the tube shall be measured immediately. Filter material shall be backfilled outside the pipe and compacted layer by layer up to the designed height of the water intake section for this measuring point. The borehole length from the hole bottom to the top surface of the backfilled filter material constitutes the actual water intake section of the piezometer tube (which may be longer than the permeable section of the tube body) and defines the actual monitoring range of the piezometer. Therefore, the design requirements must be strictly followed during installation, with precise measurement and record filing.
The filter material shall prevent fine particles from entering the piezometer while maintaining adequate permeability. Its permeability coefficient is generally 10–100 times greater than that of the surrounding soil. Clean fine sand may be used for clayey soil or sandy loam; a mixture of fine to coarse sand may be used for gravel layers. The filter material shall be cleaned and air-dried before backfilling and placed slowly into the borehole.
(4) Hole Sealing
Bentonite balls (or highly dispersive clay balls) shall be used as the hole sealing material. After hydration in the borehole, their permeability coefficient shall be lower than that of the surrounding soil. The soil balls have varying particle diameters of 5–10 mm and shall be air-dried; exposure to direct sunlight or baking is not allowed. During sealing, the balls shall be put into the borehole one by one. If necessary, 10%–20% soil of the same type may be mixed in and compacted layer by layer. Bulk dumping is forbidden to avoid void formation. Clay shall be backfilled by compaction within the range of 1–2 m below the pipe opening. After sealing to the designed elevation, clean water shall be injected into the pipe until the water level rises above the top surface of the clay ball section to allow the clay balls to hydrate and swell.
(5) Sensitivity Test
A sensitivity test shall be conducted after the piezometer tube is installed and the hole is sealed. The water injection test method is adopted, which is generally performed during the stable period of reservoir water level. The water level inside the tube is measured before the test, and then clean water is injected into the tube. If the surrounding soil of the water intake section is loam, the injected water volume shall be equivalent to 3–5 times the volume per meter of the piezometer tube; if it is sandy material, the volume shall be 5–10 times. After injection, the water level shall be continuously observed until it returns to or approaches the pre-injection level. For clay loam, the sensitivity is qualified if the water level drops back to the original level within five days after water injection. For sandy loam, qualification is achieved if the water level returns to the original level within one day. For gravel soil, it is qualified if the water level returns to the original level within 1–2 hours or the water level rise after injection is less than 3–5 m.
(6) Protection of Pipe Opening
After passing the sensitivity test, a pipe opening protection device shall be installed as soon as possible. The protection device adopts a cast-in-place concrete base or brick masonry with embedded expansion bolts, on which a steel protective cover is mounted. This structure is simple and sturdy, preventing rainwater inflow and damage by people and livestock. It is lockable and easy to open.
(7) Construction Records
During construction, relevant forms including borehole record sheet, piezometer installation record sheet and piezometer calibration sheet shall be properly filled out.


Piezometer:
(1) Install the piezometer directly inside the piezometric tube.
(2) Before embedding, the piezometer must undergo laboratory inspection and on-site verification.
(3) Prior to installation, soak the piezometer in water for more than 2 hours to bring it to a saturated state and maintain this saturated condition.
(4) During installation, first remove the permeable stone at the end of the instrument, and apply a layer of butter or vaseline on the steel diaphragm to prevent rusting.
(5) When extending the cable, core wires of the same color must be connected together and firmly soldered. Carry out careful waterproof treatment to guarantee sealing performance.
(6) During the installation of the piezometer, carefully fill out the piezometer installation record form and its verification form.

Collection / Drainage Ditch:
For reservoirs with seepage emerging visibly at the downstream toe of the dam, a collecting ditch shall be constructed at the location where seepage water converges downstream of the dam toe. A rectangular cross-section shall be adopted. Its length shall be more than 7 times the head over the weir, and the total length shall not be less than 2 m (the lengths of the weir channel upstream and downstream of the weir plate shall be no less than 1.5 m and 0.5 m respectively). Both sides of the weir channel shall be parallel and vertical.

Weir for flow measurement:
A weir is arranged at the outlet of the drainage channel to monitor its seepage (open flow) discharge. A weir plate and a weir gauge are installed at the seepage outlet to realize automatic observation of seepage volume.

Weir installation:
(1) The flow pattern at the weir crest shall be free outflow.
(2) The measuring weir shall be installed on the straight section of the drainage ditch, and the weir channel section shall be rectangular.
(3) The weir plate shall be flat; local unevenness shall not exceed ±2 mm, and local unevenness at the weir crest shall not exceed ±1 mm. The top of the weir plate shall be horizontal, and the elevation difference between the two sides shall not exceed 1/500 of the weir width. The right-angle error of the right-angled triangular weir shall not exceed 30 arcseconds. The weir plate and side walls shall be vertical, with an inclination less than 1/200. Local unevenness of the side walls shall be less than ±5 mm. The weir plate shall be perpendicular to the side walls with an error less than 30 arcseconds. The local distance error between the two side walls shall be less than ±10 mm. The weir plate shall be made of stainless steel plate, and the downstream edge of the flow passing weir crest shall be machined to a 45° angle.
(4) The weir plate shall be perpendicular to both side walls of the weir channel and the incoming flow direction. The weir plate shall be flat and level, with a height greater than 5 times the head over the weir.
(5) The staff gauge or point gauge for measuring the head over the weir shall be installed 3 to 5 times the head over the weir upstream of the weir crest. The gauge body shall be vertical, and the elevation difference between its zero point and the weir crest elevation shall not exceed 1 mm.
(6) A stilling observation well with a screened anti-fouling pipe shall be constructed at the installation position of the staff gauge or point gauge for mounting the weir meter.
(7) After the installation of the measuring weir is completed, a calibration record shall be filled in in detail and filed for future reference.


Pole Foundation:
1. Basic surveying → Foundation earth excavation → Formwork erection → Concrete pouring → Embedded part installation → Curing → Formwork removal → Earth backfilling.
2. The foundation for the video monitoring pole for rainfall and flood monitoring and the rainfall gauge pole shall be an independent concrete foundation with dimensions of 800mm×800mm×1000mm and 100mm protruding above the ground. The concrete strength grade of the foundation is C25. (The specific dimensions shall comply with site conditions and the design scheme.)
3. The pole foundation for independent video monitoring stations and similar facilities shall be a concrete foundation with dimensions of 800mm×800mm×800mm and 100mm protruding above the ground. The concrete strength grade of the foundation is C25. (The specific dimensions shall comply with site conditions and the design scheme.)

Earthwork Excavation:
(1) Main Technical Requirements for Earthwork Excavation:
1) Unqualified topsoil, debris and other materials on the foundation surface must be removed. Pits, troughs, trenches and the like within the scope shall be backfilled in accordance with the filling requirements;
2) Excavated materials from foundation clearing, surplus spoil, debris and waste residues shall be transported to designated locations for stockpiling;
3) The actual excavation profile shall comply with the opening lines, horizontal dimensions and elevations specified in the construction drawings or designated on-site by the engineer. No under-excavation is allowed for the final foundation clearing profile after excavation.
(2) Excavation Method
The earthwork excavation quantity for a single foundation in this project is relatively small, and manual excavation is mainly adopted. After balancing the earthwork for filling, the excavated soil shall be promptly transported to designated locations for stockpiling to prevent spoil from being washed away and causing soil erosion.
All foundation excavation shall be carried out on non-rainy days. If construction is conducted in the rainy season, technical measures shall be implemented to guarantee the quality of foundation works and safe construction, so as to effectively prevent rainwater from scouring the dam and eroding the foundation soil.
The construction site shall be cleared first before construction. Surveyors shall set out lines according to the design drawings, mark the excavation boundary lines and indicate the excavation depth.
(3) Earthwork Backfilling
1) After the completion of foundation excavation, earth-rock backfilling shall be carried out in a timely manner to restore the original terrain. Earthwork backfilling shall be performed in compliance with the acceptance specifications for foundation engineering construction and the requirements specified in the design drawings.
2) Before soil filling, debris at the base shall be cleared. Backfill materials shall meet the requirements of the specifications. A frog rammer shall be used for compaction; manual compaction shall be adopted where such equipment is unavailable. The moisture content of each soil layer shall be controlled at an appropriate level to improve compaction effect.
3) Measures shall be taken for construction on rainy days. Site ponding shall be drained in a timely manner. The moisture content of soil materials rises after rainfall, so the soil shall be sun-dried as early as possible to control its moisture content for backfilling.
Concrete (Reference):
1. Self-mixed concrete shall be used for construction. No admixture will be considered for concrete, while adjustments for individual parts and concrete construction in winter shall be made separately during construction as instructed by the supervising engineer.
2. Ordinary Portland cement of grade 32.5 or above shall be selected.
3. Fine aggregate is preferably natural sand with sound texture, cleanliness and good grading. The particles shall generally be subrounded and free of reactive materials. Natural sand is preferably divided into two grades by particle size.
4. Moisture Content: The moisture content of fine aggregate fed into the mixer shall be stable and less than 6%, and sufficient stockpiling time for dewatering shall be arranged.
Fineness Modulus: The fineness modulus of fine aggregate shall be controlled within the range of 2.4 to 2.8, and the variation range of the average fineness modulus shall not exceed 0.15.
5. Coarse aggregate shall be crushed stone with sound texture, cleanliness and good natural grading, and its maximum particle size shall not exceed 40 mm. Reservoir water is used for concrete mixing and curing, and its water quality satisfies the requirements for concrete mixing water.
6. All cast-in-place concrete shall be placed by horizontal continuous pouring. Concrete spreading shall be completed by combining manual work and vibrators. Manual spreading with shovels shall be adopted near formworks, dense reinforcement areas, waterstops and embedded parts, while vibrators shall be used directly for spreading at other positions.
7. Winter construction shall follow the specifications: in temperate zones, construction enters the low-temperature season when the daily average temperature falls below 3℃. Concrete construction in low-temperature seasons requires anti-freezing and anti-cracking measures.
8. Concrete pouring shall be avoided during heavy rain and torrential rain as far as possible. If concrete pouring has to be carried out on rainy days, the mix proportion shall be adjusted appropriately to ensure that the concrete strength is not affected.




Lightning Protection and Earthing:
Direct lightning protection measures shall be implemented at all monitoring stations. In accordance with the relevant provisions of GB50343-2012 *Code for Design of Lightning Protection of Electronic Information System of Buildings* and GA/T670-2006 *Technical Requirements for Lightning Surge Protection of Security and Protection Systems*, the earthing resistance shall be ≤10Ω.

Lightning protection against direct lightning strikes is generally achieved through an external lightning protection system, which forms a complete electrical path consisting of air-termination systems (lightning rods, lightning strips, lightning meshes, lightning conductors), down conductors and grounding modules to discharge lightning current into the earth.
1. Install stainless steel lightning rods made of Φ12 stainless steel. The grounding grid adopts three 40mm×40mm×5mm hot-dip galvanized angle steels as vertical ground electrodes. They are interconnected by 40×4mm hot-dip galvanized flat steel with a length L=1.5 m, and the burial depth of ground electrodes is ≥0.8 m. (Specific dimensions shall be subject to site conditions and design drawings.)
2. Layout of grounding electrodes: Excavate trenches for lightning grounding electrodes first, then drill vertical holes to bury the hot-dip galvanized angle steels. The length and burial spacing of vertical grounding electrodes shall be fabricated in accordance with construction drawings. Firmly weld all vertical grounding electrodes with hot-dip galvanized flat steel as required by design, connect them to the lightning rods via down conductors, and then backfill with soil. The down conductors are connected to the horizontal grounding electrodes from the side of the foundation through connectors.
3. During on-site construction, a precision earth resistance tester shall be used for resistance measurement, and the grounding resistance shall be ≤10Ω.
Sample Construction:
Option 1: Three 1.5 m galvanized angle steels (50*50*5 mm) shall be driven into the ground in a triangular arrangement. The embedding depth of each angle steel shall be at least 0.8 m, and the spacing shall be at least 1.5 m.
Option 2: Three 1.5 m galvanized angle steels (50*50*5 mm) shall be driven into the ground in a linear arrangement. The embedding depth of each angle steel shall be at least 0.8 m, and the spacing shall be at least 1.5 m.
The lightning rod adopts 12 mm galvanized round steel, whose top end shall extend at least 600 mm above the highest point of the vertical pole. The lightning round steel is fixed to the vertical pole with hoops.
For both options, the top ends of the three angle steels shall be welded with galvanized flat steel (50*5 mm). Galvanized flat steel (50*5 mm) shall be welded to one of the angle steels to extend above the ground and connect to the bottom end of the lightning round steel by welding.


Welcome to leave a message for consultation
Inquiry